New Mosque Project

PROJECT INTRODUCTION:

Ahmadiyya Muslim Community Complex Comprises of Masjid Building-A, Existing Prayer Hall-B, Commercial Kitchen-C, Mission House-D and Site Civil work  (New Main Parking ). As per the contract with JM Design Construction the estimated completion time is 9 months. Here after find the site progress status up to date.

SITE CIVIL WORK

  • Civil work permit process completed and issued by the city of Allen and contractor mobilization was started on 08-21-2017.
  • Silt fence installed at job site as per city requirement.
  • Site cleaning and required trees and bushes removal at west side is done.
  • All underground services marked inside the property limit.
  • Grading and layout started for new parking area.
  • Existing sprinkler system under new parking area is removed and the rest is preserved and activated.
  • Existing concrete removed and hauled from the job site as per civil plan

MASJID-A (NEW WORSHIP CENTER)
Building permit under process

EXISTING PRAYER HALL-B (FUTURE COMMUNITY HALL)
Building permit under process.

NEW COMMERCIAL KITCHEN-C
Building permit under process.

NEW MISSION HOUSE-D
Building permit under process.

GENERAL NOTES:

  • There is add on list of some small items forwarded to the contractor by the Jamat Vice president for pricing and contractor is working on items price quote and will submit next week for Client review and approval.
  • All buildings permits submission reviewed by the city of Allen officials and asked for additional information from Design Architect to complete the approval process.
  • Contractor is requested to submit schedule of work

JOB SITE PROGRESS:

Screen Shot 2017-09-11 at 6.16.35 PM.png
The silt fence fixed along with existing steel fence at south side.
Screen Shot 2017-09-11 at 6.16.43 PM.png
Site cleaning and working on existing sprinkler system.
Screen Shot 2017-09-11 at 6.16.51 PM
Site cleaning and Removal of Trees and Bushes at west side boundary.
Screen Shot 2017-09-11 at 6.17.00 PM
Existing sprinkler system is preserved and reconnected.
Screen Shot 2017-09-11 at 6.17.06 PM
Existing sprinkler system is preserved and reconnected.
Screen Shot 2017-09-11 at 6.17.34 PM
Grading under progress for new parking area.
Screen Shot 2017-09-11 at 6.17.28 PM
Grading under progress for new parking area.
Screen Shot 2017-09-11 at 6.17.21 PM
Grading under progress for new parking area.
Screen Shot 2017-09-11 at 6.17.14 PM
Grading under progress for new parking area.
Screen Shot 2017-09-11 at 6.17.47 PM
Main Parking Layout and Curb form work in progress.
Screen Shot 2017-09-11 at 6.17.41 PM
Main Parking Layout and Curb form work in progress.

 


 

Status Updates:

26 Apr 2017: We signed contract with the general contractor for the Phase 1 of the project.

10 Dec 2016: A lawyer is identified and working on construction contract. There are some minor changes by the architect on the kitchen and that will be updated with the city.

01 Jun 2015: We are now closing all required permits, Insha Allah, and have already started contacting potential bids for the contractor. We have also started collecting the funds promised and hope to start work on the ground soon, Insha Allah!

23 Jan 2015: City of Allen has approved our plan for the Mosque project. Alhamdulillah. We are now entering the next phase in the program which will start with obtaining building permit. Please keep praying and supporting the program!

26 Nov 2014: Our architect Mr. Ben Cortez has submitted the final documents with all changes per City demands. City of Allen told us there will not be no more hearings – which indicates that most of the questions are already answered and most of the feedback is already taken care in the design.

Here are a few documents while we wait to see the new Mosque with our physical eyes

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

Create a website or blog at WordPress.com

Up ↑